Courtenay Daycare Project Update

Construction is progressing steadily at the Courtenay Daycare project, with foundation work now complete and the first round of prefabricated wall panels installed in just one week. With the concrete core in place, crews have already begun standing exterior and interior steel stud walls across the slab—marking a key transition from groundwork to vertical construction. […]

Somenos Project Update

This 6-storey, 210-unit building has begun with the installation of the LBS superstructure, with concrete cores established and steel assemblies progressing steadily across the site. Our prefabricated floor system continues to support reliable scheduling and cost control, ensuring efficient installation and consistent quality. Each level is reviewed through the LBS floor-by-floor quality checklist, maintaining precision […]